UAZ - Broward County Water and Sewer Projects

UAZ 310 Water System Improvements

TCP Ravenswood & Stirling Rd Construction - 

7/21/2016

The UAZ 310 Project is scheduled to be substantially complete by November 6, 2016 and final completion is scheduled for January 5, 2017.  The water main work done on Ravenswood Road is scheduled to be completed by the middle of September.  
The water main installation on Striling Road is scheduled to be completed the last week of July.  Once the system is tested and certified, there are several water main and water service connections that will have to be made.  Restoration work began July 22nd on Stirling Road.  The restoration work for the water main is anticipated to take another 3 to 4 weeks to complete with restoration of the tie-in areas taking place after they are done. the work on Stirling Road should be completed by the middle to end of October. 
TCP Ravenswood Stirling Rd Construction 13

UAZ Road Restoration



UAZ Project Completed
Broward County Water & Wastewater Services Division will be working on restoring the roads in the affected areas over the next three weeks. They will be overlaying and milling the other half of the road  so full restoration is completed in each neighborhood affected by the project. Thank you for your understanding and patience. 

UAZ ROAD RESTORATION PHOTOS

MAP OF AREA AFFECTED: 

UAZ ROAD RESTORATION MAP
http://daniabeachfl.gov/uaz